Local Media Tour Taum Sauk Upper Reservoir Site
|
July 1, 2009
|
|
|
Reporters toured the Taum Sauk upper reservoir rebuild project during an event sponsored by AmerenUE on June 29.
More than 2.1 million cubic yards of roller-compacted concrete have been poured and the new design incorporates added safety features, such as redundant water-level sensors and continuous video monitoring. The rebuild project employs more than 600 workers and is expected to be complete during the first half of 2010. View video.
|
|
|

|
Craig Giesmann, managing supervisor, hydro engineering, guides reporters through a tour of Taum Sauk.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|