A Construction Supervisor will be dedicated to your project to ensure the construction is completed in accordance with all rules and regulations.
A. Regulator
B. Meter Bar
C. Customer Piping
D. Gas Meter
E. Meter Valve, Tracer Wire, Bracket
DO NOT bury the gas meter valve.
A - DO NOT grade to unfinished level - grade must be within 6" of the final grade.
B - DO NOT block the construction zone.
C - DO NOT disturb locates.
DO NOT crowd equipment. There is inadequate clearance between the gas service and electric meter. The electric meter is classified as an ignition source. A minimum of 3 feet is required between an ignition source and a gas regulator relief vent.
DO NOT install Corrugated Stainless Steel Tubing (CSST) through an exterior wall. Nor can it be used for exterior gas piping.